Photo report from the construction site of the SYMBOL residential complex for June 2023 from the Credo company:
The floor slab of the 4th floor was concreted
The vertical structures of the 5th floor were completed
The floor slab of the 5th floor was concreted
The brickwork of the external and internal walls of the 2-3 floors has begun
We are starting work on the installation of vertical structures on the 6th floor